U.S. Navy Prepares for Third Zumwalt Hypersonic Upgrade

Zumwalt Class Guided Missile Destroyer USS Michael Monsoor
PACIFIC OCEAN (February 10, 2024) — The Zumwalt Class Guided Missile Destroyer USS Michael Monsoor (DDG 1001) breaks away from the Henry J. Kaiser-class fleet replenishment oiler USNS Pecos (T-AO 197) shortly before sunset after taking on fuel. (U.S. Navy photo by Chief Mass Communication Specialist Mark D. Faram)
Share

The U.S. Navy is preparing to begin a more than two-year overhaul of USS Michael Monsoor in 2028 as the third Zumwalt-class destroyer to receive the service’s new Conventional Prompt Strike hypersonic missile system.

The U.S. Navy is seeking industry input ahead of a major overhaul of its second Zumwalt-class guided-missile destroyer, USS Michael Monsoor (DDG-1001), that will equip the stealth warship with new long-range hypersonic missiles and overhaul several of its onboard combat and engineering systems. Michael Monsoor‘s modernization follows the start of CPS depot modernizations to USS Zumwalt (DDG-1000) and USS Lyndon B. Johnson (DDG-1002).

The Naval Sea Systems Command (NAVSEA) announced Nov. 17 that it will host an industry day in Washington, D.C., on Dec. 9 to assess shipyard capabilities and technical requirements for the destroyer’s upcoming Conventional Prompt Strike (CPS) Depot Modernization Period (DMP), scheduled to begin in May 2028 and conclude in August 2030.

According to NAVSEA, the 27-month modernization effort will require “large-scale structural modifications” and compartment reconfiguration (mirroring previous CPS conversions) to accommodate the new CPS payload modules and launch infrastructure, alongside upgrades to the destroyer’s combat systems, computing architecture, electrical distribution, and cooling equipment.

The service is replacing each ship’s 155mm Advanced Gun Systems with large-diameter vertical launch tubes designed to accommodate the joint service CPS missiles, which Naval News previously reported are slated for future storage at Naval Weapons Station Yorktown.

The Navy is also planning a comprehensive modernization of the ship’s Total Ship Computing Environment (TSCE), including new hardware and software, open-architecture improvements, and interfaces needed to integrate the hypersonic weapon into the destroyer’s existing combat systems.

Additional modifications will focus on expanding the ship’s electrical and thermal management capacity, including improvements to power conversion and distribution systems and high-efficiency chilled-water cooling equipment.

Hypersonic CPS
NAVSEA photos detailing hypersonic integration on USS Zumwalt (DDG-1000) between January and October of 2024.

The announcement provides one of the clearest publicly disclosed schedules yet for the second Zumwalt-class destroyer’s hypersonic conversion, establishing a May 2028 start date and August 2030 completion target for the work.

Once complete in 2030, the service will have a trio of CPS-armed destroyers, which it plans to relocate to Pearl Harbor alongside a number of guided missile submarines over the next several years as a modern “Battleship Row”.